Project Informations

Erikli-Akocak Regulators and Akocak HEPP Project

Owner : Akenerji Power Generation Industry J.S.C.

Name of Project :Trabzon Araklı Erikli-Akocak Regulators and Akocak HEPP Project

Project Informations :

a)Derivation Tunnel : 3284 m

b)Energy Tunnel : 6500 m

c)Santral Building

d)Coercive Bibe : 1100 metre

e)Regulator : 2

f)Turbine : 2

g)Installed Power : 80 MW

Contract Date : 27.06.2006

Last Situation of Project : All tunnels was driven and concreted 4000m of tunnels.Akocak regulator whose of two regulators has been completed.Erikli regulator has been being built.Coercive bibe manufacturing continues.Construction Santral Building continues.

Completion Date : 31.12.2009

Completion  Date : 31.12.2010