Complated Projects
Continuous Projects
Erikli-Akocak Regulators and Akocak HEPP Project
Owner : Akenerji Power Generation Industry J.S.C.
Name of Project :Trabzon Araklı Erikli-Akocak Regulators and Akocak HEPP Project
a)Derivation Tunnel : 3284 m
b)Energy Tunnel : 6500 m
c)Santral Building
d)Coercive Bibe : 1100 metre
e)Regulator : 2
f)Turbine : 2
g)Installed Power : 80 MW
Contract Date : 27.06.2006
Last Situation of Project : All tunnels was driven and concreted 4000m of tunnels.Akocak regulator whose of two regulators has been completed.Erikli regulator has been being built.Coercive bibe manufacturing continues.Construction Santral Building continues.
Completion Date : 31.12.2009
Completion Date : 31.12.2010